The High Court of Jammu & Kashmir and Ladakh has ruled that the Food Corporation of India (FCI) cannot unilaterally impose financial penalties or alter the agreed hiring terms with a private godown owner by relying on internal decisions of a High Level Committee when the executed Lease and Service Agreement contains no clause authorising such deductions. Allowing an intra-court appeal filed by M/s Alpine Agro Services, the Court quashed FCI’s recovery notices and directed the Corporation to release withheld rentals preferably within two months.
A Division Bench comprising Justice Sanjeev Kumar and Justice Mohd. Yousuf Wani set aside an earlier order dismissing the contractor’s writ petition, reaffirming that administrative policy decisions cannot rewrite concluded commercial contracts without mutual consent.
Key Legal Findings & Proceedings
The controversy originated from a contract awarded to M/s Alpine Agro Services under the Private Entrepreneur Guarantee (PEG) Scheme for constructing and operating a foodgrain godown with a storage capacity of 17,500 metric tonnes at Shilvat. The FCI took over the storage facility on a Guaranteed Hiring Basis beginning in February 2015.
Under its project undertaking, the entrepreneur agreed to complete drainage works by March 2015 and black-topping of internal approach roads by September 2015. Although FCI extended the black-topping deadline to February 26, 2016, the work remained unfinished past that extended date and was eventually completed during May–June 2017. On account of this delay, FCI initially recovered ₹1,58,002 through an office order dated January 17, 2018, and later issued further recovery communications seeking to impose additional monetary penalties and retrospectively convert the hiring arrangement from Guaranteed Hiring Basis to Actual Utilization Basis, relying on minutes of an internal High Level Committee.
Examining the Lease and Service Agreement, the Division Bench clarified that while the contractor had indeed defaulted in meeting the extended deadline for black-topping the internal roads, that breach did not automatically confer power upon FCI to levy unilateral penalties or modify the rental structure. “In the absence of any specific clause in the terms and conditions of the Lease and Service Agreement executed between the appellant and the respondent-Corporation, the respondent-Corporation could not have unilaterally imposed a penalty, that too on the basis of calculations made at its own level,” the Court held.
The judges further emphasised that an internal administrative decision—even if adopted to ensure uniformity in dealing with contractors—cannot become part of an existing bilateral contract or fasten fresh financial liabilities without the other party’s consent. Accordingly, the Court quashed the recovery notices and directed release of pending rentals within two months.
Institutional & Legal Significance
The judgment serves as a strong restatement of public contract law principles governing statutory corporations and state instrumentalities in India. When public-sector undertakings such as FCI enter into commercial lease and infrastructure agreements under schemes like the Private Entrepreneur Guarantee Scheme, they are bound by the express terms of the bilateral contract and cannot act as arbiters in their own cause by inventing unliquidated penalties through internal committee resolutions.
For private infrastructure developers, warehousing operators, and government contractors, the ruling underscores that remedies for contractual delay must flow strictly from agreed liquidated damages clauses or adjudication in accordance with law—not unilateral administrative recovery orders. It also reaffirms that constitutional courts will intervene in writ jurisdiction where a state agency acts arbitrarily outside the four corners of a concluded contract.